Bluestone Stage 7A - Frederick Park
Bluestone, Mt Barker Stage 7A - Frederick Park
COMPLETED
Last updated 23rd September 2024
PROJECT INFORMATION
COMPLETED
- Authority approvals
- Sewer install
- Bulk earthworks
- Stormwater line
- Watermain
- Kerbs
- Bitumen
- Common Services Trench
- Basin works
- Allotment connections
- Retaining Walls
- Footpaths
- Allotment clean-up
IN PROGRESS
- All completed
ESTIMATED ACCESS FOR
- Valuations - Available now
- Soil Testing - Unrestricted access
- Site Survey - Unrestricted access
ESTIMATED TITLES AVAILABLE
Stage titled.
SETTLEMENTS COMMENCEMENT
From June 2024* (refer to your sales contract and sales agent)
*dates are estimates only and are subject to change
September 23rd 2024 Project Update
We are pleased to advise Stage 7A, Frederick Park is now completed and open to Public. Roads are finally open following a long winter and it has been great to see builders have started individual home construction within the stage.
Our landscape team have also installed street trees within the stage in time for Spring.
For any enquiries please contact our customer support at customersupport.sa@peet.com.au.




July 10th 2024 Project Update
Civil works are on the home stretch. With the wet weather setting in, site conditions are very slippery on foot with limited access onto some allotments while the ground is wet.
Footpath works had a delayed start due to the weather however are in full progress completing all of Hassett Street. Montgomery Drive is in progress and will likely be completed once the weather conditions clear up. Linthorp Street is currently being prepped.
Retaining walls are now complete with backfill remaining on a few allotments.
Completion of Stage 7A has been pushed back to the second half of July (weather pending) and as previously advised, site fences will remain during the construction period and roads will open to the public once Practical completion is reached.
For builders access for engineering purposes please contact our customer support at customersupport.sa@peet.com.au for access details. We thank you for your patience.
Bulk Earthworks > completed
Stormwater Install > completed
Water Main Install > completed
Roadworks > completed
Asphalt > completed
Kerb Installation > completed
Basin Civil Works > completed
CST Works > completed
Retaining Walls > 100%sleepers (backfill in progress)
Footpaths > in progress
Second Fix > in progress
Line Marking > anticipated mid July






June 12th 2024 Project Update
Civil Works have hit the cooler weather in Mt Barker but are progressing on site with Common Service Trenches now closed up and completed.
With the footpaths due to pour following the long weekend, weather delays have pushed the program back to the coming weeks.
Retaining walls are progressing with sleepers now completed on the lots south of Linthorp and back fill remaining to be completed in the second half of June.
Remaining retaining walls are being constructed East of the reserve and are due to be completed by the end of June.
As we approach the final stage of the construction program, outstanding works are now subject to the incoming winter weather and completion of 7A is now anticipated for the beginning of July.
Second fix has commenced with light poles dues to be installed at the end of June. Site fences will remain during the construction period and will open roads to public once Practical completion is reached.
For builders access for engineering purposes please contact our customer support at customersupport.sa@peet.com.au for access details. We thank you for your patience.
Bulk Earthworks > completed
Stormwater Install > completed
Water Main Install > completed
Roadworks > completed
Asphalt > completed
Kerb Installation > completed
Basin Civil Works > completed
CST Works > completed
Retaining Walls > 90% steel / 80% on sleepers
Footpaths > commenced
Second Fix > commenced
Line Marking > anticipated end June







May 14th 2024 Project Update
Civil works are nearing the final stages of construction. A few major milestones were hit this month with the kerbs completed and asphalt laid to roads.
Common Service Trenches are in progress and are due to be backfilled and completed before the end of month.
Retaining walls are taking longer than expected however a lot of progress has been made with the southern lots on Linthorp Street this month. Walls are expected to be completed in the coming weeks.
Footpath prep and pour are forecast to commence at the beginning of June. This will be last major works to be completed, with second fix of services to follow.
Bulk Earthworks > completed
Stormwater Install > completed
Water Main Install > completed
Roadworks > completed
Asphalt > completed
Kerb Installation > completed
Retaining Walls > 80% steel / 65% on sleepers
CST Works > 40%
Footpaths > commencing June
Basin Civil Works > commenced













April 10th 2024 Project Update
March saw a big push on road works with subbase rolled and kerbs commencing. By the end of this week machine kerbing will be completed, with handworks continuing on the finer details.
Retaining walls are continuing and as noted with the last update there has been some delay in the retaining program. We appreciate your patience whilst we continue works. The installation of the retaining walls is a complex process and we have been working closely with builders and engineers regarding availability for engineering access.
Common Services works have commenced- works will progress over April; footpath prep and pour to follow thereafter. We will be aiming for basecourse to be laid next week (pending weather) in readiness for asphalt to be down second half of April.
Please note, CST works will limit access for engineering on particular blocks so we will do our best to accommodate engineering access requests where reasonable.
Frederick Park works have commenced with the basin excavation taking shape. As we get into the final stages of construction, we also start to see wet weather. We anticipate Practical completion early June
Bulk Earthworks > completed
Stormwater Install > completed
Water Main Install > completed
Retaining Walls > 50% steel / 45% on sleepers
Roadworks > 100% subgrade / 100% subbase / 0% basecourse
Asphalt > second half of April
Kerb Installation > 95%
CST Works > in progress
Footpaths > commencing May
Basin Civil Works > commenced









March 19th 2024 Project Update
Stage 7A has made big progress in the past week with main services complete and road works well underway with the first run of kerbs down on Hassett Street.
Engineering access for Hassett blocks has now been pushed back to the start of April due to a slight delay with our retaining program. We are aiming to see the majority of retaining sleepers placed before Easter.
Kerbs are forecast to be completed by early April and asphalt down in the second half of April.
In even more exciting news, Frederick Park civils will commence in the next couple of months, so watch this space transform!
Bulk Earthworks > completed
Stormwater install > completed
Water main install > completed
Retaining walls in progress > 65% on drilling and posts / 35% on sleepers
Roadworks >50% subgrade / 30% subbase
Kerb installation >30%
CST works > commencing April
Footpaths > commencing May






March 2024 Project Update
Stage 7A is taking shape with Lot Benching completed. Reserve earthworks will start to commence next month.
Underground infrastructure are well underway with the last of the watermains to be completed this week, and CST crossings currently being completed. Common Services (Power, Gas, NBN) will commence next month.
Retaining walls are in progress, with the main focus being completing Hassett St to enable early engineering access for these blocks in the next couple weeks. The retaining crew are halfway through drilling for the stage and sleepers are being completed along Hassett St. Backfilling will commence within the next week.
Roadworks have also commenced following underground services with subgrade being laid on Hassett St in readiness for kerbs to commence at the end of the week.
Bulk Earthworks > completed
Retaining walls in progress > 50% on drilling and posts / 25% on sleepers
Stormwater install > completed
Water main install > 95% completed
Roadworks > commenced
Kerb installation > commencing mid March
CST works > commencing April







February 2024 Project Update
Bulk earthworks are almost complete with the last of Linthorp St currently being benched.
Underground infrastructure is in progress; sewer main is complete, stormwater pits are mostly installed with the main line to follow. Water mains scheduled to commence in the coming weeks.
Retaining walls have recently commenced with Hassett St well underway.
Roadworks are scheduled to commence early March in preparation for the installation of kerbs.
Bulk Earthworks are nearly finished > 95% completed
Retaining walls in progress > 10% completed
Sewer main install > 100% completed
Stormwater install > 30% completed
Water main install > due to commence mid-Feb
Roadworks > due to commence late Feb/early March
Kerb installation > due to commence mid March







January 2024 Project Update
Bulk Earthworks are nearly finished > 80% completed
Retaining walls have commenced > 5% completed
Sewer install has begun > 30% completed
Stormwater to commence early next week





December 2023 Project Update
Bulk Earthworks are well underway with Hassett St blocks benched
Retaining walls have commenced
Sewer install are due to start soon


